Bangladesh Enters Nuclear Era as Rooppur Plant Feeds First Power into National Grid
The 1,200MW unit supplied up to 350MW on a trial basis as engineers began testing its stability and integration with the national power system.

In a landmark moment for the country's energy sector, the first unit of the Rooppur Nuclear Power Plant successfully connected to Bangladesh's national grid on Tuesday and began supplying electricity on a trial basis. The development, which took place in the afternoon, positions Bangladesh as the 33rd nation in the world to generate nuclear power and brings a project that has been under construction for nearly a decade one step closer to commercial operation.
The synchronisation occurred at approximately 3:16 pm at the plant site in Ishurdi, Pabna. Initial output climbed to around 350 megawatts before operators deliberately lowered it to roughly 300 megawatts to assess how the national grid would respond to the new source of power. Science and Technology Minister Fakir Mahbub Anam was present during the milestone, describing it as a historic achievement for the country.
The trial is being conducted in carefully controlled stages. According to the current plan, the unit will remain connected for about eight to ten hours while engineers closely monitor the performance of the turbine, generator, and the systems that link the plant to the wider power network. It will then be disconnected for roughly 28 hours so that additional technical checks can be completed. After this break, the unit is expected to be reconnected for another four to six hours of testing. Only once these stages are successfully finished will the Bangladesh Atomic Energy Regulatory Authority consider approving the next phase of trial operation.
Rooppur consists of two Russian-designed VVER-1200 reactors, each with a capacity of 1,200 megawatts. When both units are fully operational, the plant is expected to deliver a total of 2,400 megawatts. Officials believe this output will help meet a significant portion of the country's electricity demand and reduce dependence on imported fossil fuels. Construction of the first unit began in late 2017. The project's original completion target has been revised more than once, and its overall cost has risen to approximately Tk 1.39 trillion, largely because of currency fluctuations and extended timelines.
The successful grid connection comes at a time when Bangladesh is actively seeking to diversify its energy mix. Rising global fuel prices and growing domestic demand have increased the urgency of developing more stable, baseload power sources. Nuclear energy is viewed as one of the options that can provide consistent supply once commercial operations begin. Authorities have indicated that, if the remaining tests proceed without major setbacks, the first unit could enter commercial generation in the first half of 2027, possibly as early as February. Exact dates, however, will depend on regulatory clearance and the results of ongoing technical evaluations.
For now, the focus remains on the methodical testing process. Engineers will gradually raise output levels, conduct stress tests, and verify that the plant can operate safely and stably alongside the existing national grid. The trial feed of up to 350 megawatts is therefore not the start of regular commercial supply, but rather a critical intermediate step that confirms the plant can successfully transfer nuclear-generated electricity into Bangladesh's power system.
The achievement has been widely noted as a major step forward for the country's long-term energy security. While challenges related to cost, timeline, and future waste management remain, Tuesday's grid connection has given concrete evidence that the Rooppur project is progressing toward its ultimate goal of providing reliable nuclear power. As testing continues in the coming weeks and months, attention will stay on whether the plant can move from this experimental phase to sustained commercial operation and begin contributing meaningfully to the national electricity supply.

