Rooppur Nuclear Plant Reconnects to Grid in Second Trial, Boosting Bangladesh’s Energy Future
The 300–350MW test will assess the reactor's turbine, generator, control systems and grid-linking equipment before commercial operation targeted for 2027.

Bangladesh's long-awaited nuclear power project advanced another step on Monday when the first unit of the Rooppur Nuclear Power Plant began supplying electricity to the national grid for the second time. Engineers at the facility in Ishurdi, Pabna, initiated the fresh grid connection trial at approximately 10:20 a.m. on 23 November 2026, with Unit-1 expected to deliver between 300 and 350 megawatts during the test period.
The trial is scheduled to run for 10 to 24 hours. During this window, project teams will carefully monitor the performance of the turbine, generator, control systems, and the equipment that links the plant to the national grid. The goal is to confirm that the reactor can operate stably and transfer power safely under real conditions. Electricity produced during the test can reach consumers, though authorities have stressed that uninterrupted supply is not yet guaranteed while the plant remains in the testing phase.
Power Grid Bangladesh PLC is managing grid balance throughout the trial, while the Bangladesh Power Development Board is overseeing the supply side. Project Director Dr Md Kabir Hossain confirmed that the second connection forms part of a structured series of technical evaluations required before the unit can move closer to commercial operation.
This latest run follows the plant's first successful synchronisation with the grid on 17 November. On that day, Unit-1 supplied up to 350 MW for roughly eight and a half hours before being disconnected for further checks. Engineers used the interval between the two trials to assess equipment performance and make any necessary adjustments. The fact that the second connection began smoothly six days later is being viewed by project officials as a positive indicator of progress.
Rooppur is Bangladesh's first nuclear power plant. Built with Russian technical assistance, it is designed around two VVER-1200 reactors, each with a capacity of 1,200 MW. Once both units reach full commercial service, the plant is expected to contribute a meaningful share of the country's electricity demand and reduce reliance on imported fossil fuels. Commercial operation of Unit-1 is currently targeted for 2027, subject to the successful completion of remaining tests and regulatory approvals from the Bangladesh Atomic Energy Regulatory Authority.
The repeated grid connections mark a visible milestone for a project that has been under construction for years. For decades Bangladesh has depended heavily on gas, imported coal, and oil for power generation. A stable nuclear contribution could improve energy security, support industrial growth, and help meet rising electricity demand from households and factories. Each successful trial brings the plant closer to that long-term goal.
Local communities near Ishurdi have watched the cooling towers and reactor buildings rise over the past several years. While the plant is still in the testing stage, the sight of power flowing into the national grid has generated cautious optimism among residents and energy planners alike. Officials continue to emphasise safety protocols and transparent monitoring at every stage of the process.
Further tests are expected in the coming weeks and months. These will examine the plant's ability to operate at different output levels and respond to varying grid conditions. Only after the full sequence of trials is completed and regulatory clearance is obtained will Unit-1 be ready for sustained commercial generation.
The second grid connection on Monday is therefore more than a technical exercise. It represents another concrete step in Bangladesh's effort to diversify its energy mix and bring its first nuclear power plant into regular service. As the trial continues through the day, engineers will gather data that will shape the next phase of commissioning and, ultimately, the country's nuclear energy future.